November 22, 2026, Wells County, Data Panel, Part 5 of 5

Wells County Data Center Panel

November 22, 2026

NDFU stated that currently no policy on Data Center

Terry: Executive Director, lawyer

Seth Sevenson with NPEC

Warren Strand is with Well County Zoning

Data Centers:  Hyperscale's – Phone, GPS, not flock, bank, any application, your help care, crypto mining, AI learning

NPZC:  need steady, transmission lines, selling electricity to Data Center can lower power distribution, taxes sent back to township entities.

WCZB:  Slow down, be responsible, need to be set in place.  Does our county want Data Center, lights, and roads?

Seth large load:  Basin Electric imperiality study, contact before moving forward.

Terry:  Why ND?  Answer:  Cold, windy weather, the cost of electricity and land

Warren:  Conversations don’t get real until projects are close.  Need to learn from Williams County and Ellendale.

Terry:  Williams county no ordinance in place.  Lots of Problems, lite pollution, road use only takes certain routes.  Flat State: Noise pollution 3rd in station; plant trees; build Acoustic barriers and shields.

Warren:  We need to learn & get set in place.

Terry:  H20 north of Nebraska can use close loop; one million gallons, flush, use-60/40 glycol/H20

Public:  NDA; local elective leaders; needs improvement; needs more transparency; How many people to run Data Center; first phase 100 jobs- plumbers, electricians, and security = $64,000; Why use prime farmland? Natural Gas???;

Closing: Terry – Do your research? Warren – reach out for conversation.